SERVICES
SHUTDOWNS / TURNAROUNDS
From shutdowns to turnarounds, no matter how large or small, the more challenging the better, give us a call and we will be happy to send a representative to your facility to provide a comprehensive proposal.
Team SIC is on YOUR schedule…
Southern Industrial Contractors has recently completed a new infeed conveyor foundation for International Paper – Texarkana mill located in Queen City, Texas. This project involved the installation of 16 H-piles 14 X 117 which were 80′ long as well as installation of 250 cubic yards of structural concrete. The existing plant’s log cranes and infeed deck could only be shut down for 5 days, therefore, the work had to be completed in less than 5 days. SIC started this work at 1 AM on Monday morning and all work was completed by Friday at 12 noon. SIC mobilized two crawler cranes to the worksite which were a 250-ton crawler crane and an 80-ton crawler crane along with pile hammers and hydraulic drills for the pile installation. The 16 H-piles were completed within the first 36 hours of the shutdown.